The proposed project consists of construction of a new 330 kV power
transmission line.
This public sector project involves construction of a new 124 km power
transmission line connecting the Usatove and Ajalyk substations in the Odessa
region. The project will also include the expansion of these two substations.
The line will be constructed along a new route and as part of the assessment a
number of alternative routes were considered.
The objective of this project is to increase the reliability of power supply
to consumers in the Odessa region and to decrease dependency on unstable power
supply from Moldova. The modernization of the substations as well as increased
reliability of the power line will increase efficiency will thus have indirect
environmental benefits.
There is a project summary document available for this project.
|