Project name:TSA Air Navigation Systems
Country:Tajikistan
Project number:15857
Business sector:Transport
Public/Private:Public
Environmental category:B
Board date:4 September 2001
Status:Signed
Date PSD disclosed:
Date PSD updated:
1 March 2001
3 October 2001
Help

Subscribe to PSD
email alerts

Related links
Tajikistan homepage
Transport homepage
Air industry investments boost Tajik economy [Story]
Projects in Tajikistan [EBRD - Countries]

Project description
and objectives:

Proposed loan to modernise Tajikistan's ageing air navigation equipment and to support the restructuring of the aviation sector.

The project aims to:

  • replace ageing equipment for air navigation services;
  • implement reform of the aviation sector in Tajikistan;
  • support corporate restructuring of TSA.

Transition impact:

The Aviation Restructuring Study, financed by technical cooperation (TC) funding, resulted in a number of recommendations. TC assistance attached to the present project will provide the means to implement these recommendations. They include the transfer of TSA's regulatory function to an independent entity and the creation of separate business units. The modernisation of Tajikistan's ageing air navigation equipment will ensure the safety of Tajik airspace.

The client:

Tajikistan State Air (TSA) is a wholly state-owned company.

EBRD finance:

Loan of up to US$ 5.5 million (€6.2 million). Approximately US$ 2 million grant was approved to be funded from the Japan Fund for Post Conflict Support and Japan Europe Co-operation Fund.

Total project cost:

Approximately US$ 7.5 million (€8.5 million).

Environmental impact:

The project has been screened B0, requiring an environmental analysis. The environmental impact associated with air navigation projects such as this one is not likely to be significant. It is generally limited to construction practices and includes issues such as dust, noise, possible ground or surface water pollution, waste disposal, worker health and safety issues, and use of hazardous materials. There could also be environmental impact associated with the siting and construction of access roads and radar equipment. Environmental due diligence will be carried out and necessary mitigation measures will be developed prior to the project's final approval.

Technical
cooperation:

TC funding will:

  • assist the establishment of a civil aviation department;
  • assist the procurement and implementation of supervision;
  • support the establishment of a cost accounting and management information system.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

EBRD contact:

Bakhtiyor Faiziev, Operation Leader: faizievb@ebrd.com

Procurement or tendering
opportunities:

Visit EBRD Procurement
Enquiries: Tel: +44 20 7338 6794; Fax: +44 20 7338 7472, Email: procurement@ebrd.com

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback