Project name:Armenian Copper Programme
Country:Armenia
Project number:23169
Business sector:General manufacturing
Public/Private:Private
Environmental category:C
Board date:19 November 2002
Status:Completed
Date PSD disclosed:
Date PSD updated:
16 October 2002
17 December 2002
Help

Subscribe to PSD
email alerts

Related links
Armenia homepage
Armenia receives cross-sector support from the EBRD [Press Release]

Project description
and objectives:

A proposed 2-year revolving working capital facility to enable Armenian Copper Programme to fully utilise the current production capacity of its copper smelter in Alaverdi, Armenia.

The project will assist Armenian Copper Programme in stabilising production levels through the provision of working capital, thereby improving the efficiency of the production process. Enhanced profitability will enable the company to introduce environmental improvements.

Transition impact:

The project would provide support for the growth and restructuring of an export-oriented Armenian corporate, which operates in the poorer northern part of the country. The project requires the company to introduce environmental improvements and to apply principles of good corporate governance.

The client:

Armenian Copper Programme is a closed joint-stock company incorporated in Armenia. Armenian Copper Programme produces blister copper from copper concentrate and operates a small copper mine to supplement its external supplies of copper concentrate.

EBRD finance:

Loan of US$ 3 million (€3.1 million).

Total project cost:

US$ 3 million (€3.1 million).

Environmental impact:

The project has been screened C /1, requiring an environmental audit which has been carried out by international consultants.

The audit provided recommendations for an Environmental Action Plan (EAP) which would include short-term, low cost remediation measures, and a medium to longer-term higher cost modernisation programme. The EAP has been reviewed by ACP and the short-term EAP agreed in principle. The implementation of the short-term EAP will allow to address only high priority issues, such as dust emission and effluent discharge control. However, it will not bring the facilities fully into compliance with international good practice, WB and EU environmental, health and safety standards. This can only be achieved through the implementation of a long-term modernisation programme, currently at an initial stage of development, and which will be further developed under the planned working capital facility.

Technical
cooperation:

The environmental audit of the current operations of the client was financed by TC funds made available by the Canadian government. The cost of €25,000 will be reimbursed by the client at the first disbursement of the working capital facility.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

Company contact:

 

EBRD contact:

Natalia Gammans, Operation Leader: gammansn@ebrd.com

Business opportunities:

For business opportunities or procurement, contact the client company.

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback