EBRD homepage
About the EBRD
News & events
Publications
Countries & topics
Projects
 
Project summaries

Approved & signed

Case studies

Environmental documents

Evaluation
Apply for financing
Environment
Capital markets
Working together
 

 

Project summary document

Project name:Narva Power
Country:Estonia
Project number:27497
Business sector:Power and Energy
Public/Private:Public
Environmental category:A
Board date:
Status:Cancelled
Date PSD disclosed:
Date PSD updated:
11 July 2002
22 January 2003
Help

Subscribe to PSD
email alerts

Related links
Estonia homepage
Power and Energy homepage
Narva Power [Environmental Impact Assessment]

Project description
and objectives:

Proposed corporate loan to Eesti Energia to finance investment in transmission and distribution, and rehabilitation at the existing Balti and Eesti power stations that would utilise energy-efficient technology with a high degree of pollution control and environmental remediation.

The EBRD would provide funds to finance investment at each of the Balti and Eesti power stations (the Narva Power programme). The Narva Power investment programme comprises three distinct elements: repowering projects, renovation projects and environmental remediation. The programme has three main objectives: (1) to reduce the total level of sulphur dioxide (SO2) emissions to enable Estonia to meet its international environmental obligations with regard to SO2; (2) to address other environmental issues at the power plants such as particulate emission, ash pond rehabilitation, soil and ground water contamination and water plant renovation; and (3) to improve the efficiency and reliability of the power plants. The repowering investments will boost fuel efficiency by 20 per cent by increasing the efficiency by about 6.5 per cent.

The Project will also include investment in transmission and distribution to increase efficiency, reduce losses and extend service to new customers.

Transition impact:

The Project will be supported by an agreement with the Government and the Company to (1) establish a grid code to support Estonia’s goal to create a competitive electricity market; (2) further separate transmission, dispatch and distribution into new legal entities to create more transparent operations; and (3) to establish a tariff methodology for the sector.

The client:

Eesti Energia is the vertically integrated Estonian electricity utility and 100 per cent owner of Narva Power, a subsidiary company that owns the Balti and Eesti power stations. Eesti Energia is owned 100 per cent by the Estonian Government.

EBRD finance:

The EBRD expects to provide €50-100 million as a 15-year parallel loan alongside the Nordic Investment Bank, KfW and bond investors. Total debt financing is expected to be approximately €350 million.

Total project cost:

€650 million through 2007.

Environmental impact:

Summary of Environmental Impacts

The environmental studies carried out to date have shown that Narva Power is in compliance with current Estonian environmental laws and requirements. The investment programme has been designed to continue the operation of Narva Power Plants in compliance with increasingly stringent Estonian, EU and International environmental requirements and will result in significant reduction of their environmental impact.

The key conclusions of the environmental assessment of the project are:

  • Narva Power's two power stations, Balti and Eesti, are Estonia’s major sources of air pollutants and urgently require rehabilitation.

  • The Narva Power investment programme, which has mainly environmental objectives, will result in significant environmental benefits, enabling Narva Power to meet increasingly stringent future environmental requirements.

  • The project will reduce air emissions of SO2 by 44 per cent and of particulates by 93 per cent. NOX and CO2 emissions will also be reduced.

  • Narva Power's transboundary sulphur load to adjacent areas in Finland and Russia is expected to reduce in the same proportion as the emissions.

  • The project will result in additional environmental benefits through clean-up of contaminated soil, rehabilitation of the waste management system, reclamation of an ash disposal area, closure and encapsulation of industrial landfills, removal and repair of the present asbestos insulation, occupational health and safety programmes and introduction of ISO 14001 Environmental Management System.

  • Further environmental mitigation measures and improvements will be addressed in an Environmental Action Plan to be implemented in addition to the investment programme.

  • Any potential adverse environmental impacts of the construction works are assessed to be limited both in time and scale.

The complete Executive Summary of the Environmental Impacts of the Narva Power Plants is available at EBRD's web site: www.ebrd.com

Eesti Energia is currently carrying out a comprehensive study of the environmental impacts of the Narva Power investment programme on the request of the Estonian Ministry of the Environment (MoE). The study includes consultations with the public as required under Estonian law. Due to Narva Power’s transboundary environmental issues, the Estonian MoE has also notified the relevant Finnish and Russian authorities in accordance with the UNECE Convention on Environmental Impact Assessment in a Transboundary Context as well as the Estonian-Finnish intergovernmental agreement on assessment of transboundary environmental impact. Further information on the study, public consultation process and the environmental impacts of Narva Power Plants is available at Eesti Energia's web site: www.energia.ee

There is an Environmental Impact Assesment available for this project.

Technical
cooperation:

None.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

EBRD contact:

Richard Stanaro, Operation Leader: stanaror@ebrd.com

Procurement or tendering
opportunities:

Visit EBRD Procurement
Enquiries: Tel: +44 20 7338 6794; Fax: +44 20 7338 7472, Email: procurement@ebrd.com

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback