|
Environmental classification and rationale
BOT Elektrownia
Belchatow is one of the largest conventional power plants in Europe, with the
installed capacity of 4440 MWe in 12 units. This lignite fired plant was
designed in the 1970’s and was gradually commissioned throughout the 1980’s.
The project was screened A/1, requiring an environmental impact assessment
(EIA) and environmental audit in line with the Bank’s Environmental Policy and
Public Information Policy. The project is also subject to Polish EIA and IPPC
requirements. An IPPC permit application will be undertaken prior to
commissioning the plant.
Information reviewed during the environmental appraisal
An
Environmental Audit and Analysis is being undertaken as part of the Banks due
diligence.
Information received includes the following;
-
Environmental Impact Statement for new 833 MWe power unit, Executive Summary,
July 2005 (in Polish and English)
-
Environmental Impact Statement for new 833 MWe power unit, Main Report,
Planning permit application, dated July 2005 (in Polish)
-
Assessment of the environmental impact of El. Bełchatów II, prepared by
“Energoprojekt-Warszawa” S.A., dated 1998 (in Polish)
-
Integrated Permit for BOT Elektorwnia Belchatow, dated March 31th, 2003 (in
Polish)
Members of the Bank’s Environment Department visited the site in 2000;
additional meetings were held in 2004/5. EBRD staff attended public
consultations in July 2005.
Key environmental issues and mitigation
The key environmental
issues are air emissions and waste disposal. Belchatow is a lignite fired
power station providing almost 19% of the Polish electricity supply. It is
also a significant point source emitter of SO2 and CO2 in Poland. To reduce
environmental impacts, a gradual modernization programme has been implemented
since the 1990’s, mainly aimed at improving efficiency and reducing emissions.
The plant has installed flue gas desulphurization (FGD) on 8 units, modernised
burners, optimized boiler combustion process and modernised electrostatic
precipitators (ESPs) on existing units, which has resulted in a drastic
reduction of emissions over the past decade.
The new unit and the overall modernization of the Belchatow Power Plant is
part of the long term modernization of the plant. The new 833 MWe unit will
eventually replace the oldest units at Belchatow (number 1 and 2 by 2015).
The project will enable the plant to slightly increase its generating capacity
and at the same time reduce emissions, notably SO2 and NOx
The new unit will be using state-of-the-art pollution control technology
inclusive of flue gas desulphurisation (FGD). The plant will meet the relevant
EU and Polish emission standards for particulates, SO2 and NOx, notably as
specified by the EU Large Combustion Plant Directive (2001/80/EC). The project
will make use of Best Available Techniques (BAT) as required under the IPPC
Directive and will help to reduce the overall environmental impacts associated
with generation of electricity in Poland.
The main impact from the plant will be sulphur dioxide emissions and their
impact on local air quality. An assessment was made of the impact on the local
air quality, and the modelling did not identify any exeedance of national or
EU ambient air quality standards as a result of operating the existing and new
unit.
BOT Belchatow Power Plant will operate the plant in compliance with Polish
laws and regulations as well as in accordance with EU environmental standards.
An environmental management system and continuous monitoring is incorporated
into day-to-day operations of the plant and will be upgraded during the
implementation of the modernization programme.
Given the nature of fuel used (lignite), substantial carbon emissions will be
associated with the project. This will be partially mitigated by high
efficiency of the new 833 MWe power unit and efficiency improvement of
existing units (less lignite used).
Water consumption and wastewater discharges will be minimised by a water
circulation system, flue gas emission will be emitted via the cooling tower
for the new unit, and from the existing multi-flue stack for the remaining
units.
Solid waste consisting largely of fly ash and furnace bottom ash, will be
transported as slurry to a newly constructed landfill associated with the
neighbouring lignite mine. This new landfill has been constructed in
accordance with EU and Polish environmental standards and regulations. Waste
gypsum from the wet limestone FGD scrubbing system will be used commercially.
Existing buffer storage capacity is included in the project design.
The plant will utilize an existing site and existing connections for lignite,
and auxiliary operations; this limits the new footprint of the plant. Fuel
will be supplied from the nearby operational mines. In the future an
additional 40 km high power voltage line will be constructed to serve the new
unit. Appropriate permits will be obtained in due course for this separate
development. Initial information received indicated that the environmental
impact associated with this investment is not major.
The Company has implemented an ISO 14001 Environmental Management System for
its operations.
These measures are aimed to ensure that the environmental issues will be
sufficiently managed to prevent or minimise impacts on staff and local
population as well as on the environment.
Environmental opportunities
The proposed project is expected
to bring significant environmental benefits as the new plant will be using
state-of-the-art technology and replace older polluting generating units in
Poland leading to reduced pro rata emissions. The project will also help to
satisfy future demand for electricity in Poland as old inefficient
coal/lignite fired plants are decommissioned. Moreover, the project is an
essential element in the Polish strategy to reduce sulphur dioxide emissions
from large combustion plants.
Summary of Environmental Action Plan
An Environmental Action
Plan (EAP) will be developed following the completion of the due diligence.
It is likely that the EAP will address inter alia air emission control, house
keeping and the overall management of the environment, health and safety
issues at the power plant and associated auxiliary operations such as the
landfill and the transmission line.
Disclosure of information and consultation
BOT Belchatow Power
plant has started a public consultation and disclosure programme, in
compliance with national and EBRD requirements, commencing in July 2005.
Disclosed materials
1. 2005 Environmental Impact Statement, Executive Summary in English and Polish
2. 2005 Environmental Impact Statement, Main Report in Polish
3. 2003 IPPC Permit for the BOT Elektorwnia Belchatow power plant (in Polish)
The materials are available in hard copy at the following locations in Poland:
-
The Office of the Gmina in Kleszczów; 97-410 Kleszczów, ul. Główna 47; Tel. +
48 (44) 731-31-10; e-mail:
kleszczow@kleszczow.pl
-
The Poviat Starost's Office in Bełchatów; 97-400 Bełchatów, ul. Pabianicka
17/19; Tel: +48 (44) 635 86 00; e-mail:
powiat@powiat-belchatowski.pl
-
ELBIS Sp. z o.o., Rogowiec, Belchatow. Tel. +48(44) 735 33 40; Contact: Mr
Marek Wdowiak, Technical Director.
-
BOT-Elektrownia Belchatow S.A.; Rogowiec, 97-406 Bełchatów 5, Tel: +48 (44)
632-51-32; contact: Mr Miroslaw Niewiadomski, Environment Director
-
EBRD Regional Office Warsaw, ul. Emillii Platter 52; Contact Lucyna Stanczak
An announcement about the public consultation period was made on from 30 June
to 6 July 2005 in the “Gazeta Belchatowska”, “Fakty”, “Informator
Kleszczowski” newspapers and in local radio and TV.
Additionally, the materials are available on the
BOT website and ELBIS website.
Monitoring and reporting
The Company will monitor the
environmental impact of its operations in accordance with national law and
regulations. The Bank will evaluate the project's compliance with the
applicable environmental and social requirements during the lifetime of the
project by reviewing annual environmental reports prepared for the project
covering:
(i) ongoing performance of project-specific environmental, health and safety
activities as reflected in the results of periodic and quantitative sampling
and measuring programmes, and
(ii) the status of implementation of environmental mitigation and improvement
measures. The Bank’s representatives will also conduct periodic site
supervision visits when deemed appropriate.
If required, the Bank will carry out monitoring visits to the plant.
There is an Environmental Impact Assesment available for this project.
|